Need Smart Hands / Network Field Engineers
Resources should have experience in rack & stack, cabling, WLC installations, fiber connectivity, and remote support coordination.
Primary Onsite Work
Stage equipment before cutover.
Install 2 Cisco 9800 WLCs per site.
Perform power/network cross-connects, including verifying switchport availability for WLC connections.
Install/connect required SFPs, fiber patch cords, and Ethernet patch cords as per site requirement.
Support remote team during cutover and validate installation.
Remove old WLCs, label, pack, and prepare for return shipment.
Deployment Scope
Tools / Material Readiness
Engineers should have console cable, hotspot, label maker, rack screws, and be prepared with/verify required SFP modules, fiber patch cords, and Ethernet patch cords per site.